OP
TedM
The DECC proposal is that there are 3 possible ways for a project to qualify for the extra 12 months grace period to register for ROCs. Any one of these may apply:
1. Preliminary accreditation
2. Significant financial committment
3. Grid connection delay
The evidence you have to present to OFGEM for each of these is:
1. Preliminary accreditation already granted on or before 22 July. You have to have OFGEM paperwork.
2. Showing a significant financial commitment to the project on or before 22 July. You have to provide evidence of all following 3 items to OFGEM:
a) a grid connection offer and acceptance dated on or before 22 July
b) Director's Certificate confirming land agreement in place dated no later than 22 July
c) Planning application received on or before 22 July
3. Evidence of a delay to a planned grid connection, being 3 items:
a) grid connection agreement with a delivery date no later than 31 March 2016
b) declaration that commissioning would have been complete by 31 March 2016 except for delay to grid connection
c) DNO confirmation that delay was not the fault of the generator/developer
So you have to have either 1 or 2 (a,b and c) or 3 (a, b, and c)
A grid connection offer on its own is not enough.
[edit - formatting grrr!]
1. Preliminary accreditation
2. Significant financial committment
3. Grid connection delay
The evidence you have to present to OFGEM for each of these is:
1. Preliminary accreditation already granted on or before 22 July. You have to have OFGEM paperwork.
2. Showing a significant financial commitment to the project on or before 22 July. You have to provide evidence of all following 3 items to OFGEM:
a) a grid connection offer and acceptance dated on or before 22 July
b) Director's Certificate confirming land agreement in place dated no later than 22 July
c) Planning application received on or before 22 July
3. Evidence of a delay to a planned grid connection, being 3 items:
a) grid connection agreement with a delivery date no later than 31 March 2016
b) declaration that commissioning would have been complete by 31 March 2016 except for delay to grid connection
c) DNO confirmation that delay was not the fault of the generator/developer
So you have to have either 1 or 2 (a,b and c) or 3 (a, b, and c)
A grid connection offer on its own is not enough.
[edit - formatting grrr!]
Last edited by a moderator: