How would you go about changing this unit over?
Old wylex board with Pyro mains tails. Earthed via Pyro, and all circuits via conduit.
Protrudes out the wall so I was thinking 1 of options, as I can’t see any other way round it.
Option 1
Batten on each side of the DB to the same level of the current one, crimp all cables and mount new unit over the old one.
Take a 16mm cpc from old board to new board.
Option 2
Angle grind the DB so it’s level with the wall and do same as above.
Option 3
Remove current DB completely and try to get another one in the same space, attempt to alter conduits and pyro to fit.
Don’t fancy bending pyro!
Old wylex board with Pyro mains tails. Earthed via Pyro, and all circuits via conduit.
Protrudes out the wall so I was thinking 1 of options, as I can’t see any other way round it.
Option 1
Batten on each side of the DB to the same level of the current one, crimp all cables and mount new unit over the old one.
Take a 16mm cpc from old board to new board.
Option 2
Angle grind the DB so it’s level with the wall and do same as above.
Option 3
Remove current DB completely and try to get another one in the same space, attempt to alter conduits and pyro to fit.
Don’t fancy bending pyro!