Hi guys,
Im installing some main switches in an installation to cover 3 boards.
A question i have is, they anything against the regulations or indeed bad practice to fit a single main isolator switch to cover the 3 boards or should they have 3 individual ones.
What i got is a single phase load coming out main supply into a henly block which then feeds 3 DBs. Should it be okay to pick the incoming feeds into the henly block and take then into isolator and then new meter tails from isolator back into the henly block which would then feed the 3 dbs. So basically putting the main switch before the henly block?
obv this is the cheaper and quicker solution, but i just want to make sure im not missing anything which makes this against the regulations?
thanks in advance
Im installing some main switches in an installation to cover 3 boards.
A question i have is, they anything against the regulations or indeed bad practice to fit a single main isolator switch to cover the 3 boards or should they have 3 individual ones.
What i got is a single phase load coming out main supply into a henly block which then feeds 3 DBs. Should it be okay to pick the incoming feeds into the henly block and take then into isolator and then new meter tails from isolator back into the henly block which would then feed the 3 dbs. So basically putting the main switch before the henly block?
obv this is the cheaper and quicker solution, but i just want to make sure im not missing anything which makes this against the regulations?
thanks in advance