3 weeks ago I did the first fix on a refurbishment of kitchen. I have only just had a phone call to come and do the second fix.
The customer is unhappy as the builder has said he cannot use the cable I had in position for the downlights? He has gone ahead and put the ceiling up and just left all the cable that I had neatly dangling up in the void which is now not reachable without lifting floorboards.
He had said that he would position all the downlight holes and just pull the cable through, but the customer has said that he said the cable was not in the right position and would leave a big gap in the middle of the kitchen.
I specifically left plenty of cable (about 1.5m) dangling from the ceiling at each point so he could choose where he positioned the downlights and I spaced them out fairly evenly (as much as you can when just hanging from joists waiting for the ceiling to go up). So apart from the fact that it doesn't make sense, it would have been a good idea to call me before putting the ceiling up and hiding all my cable?
I cant get hold of the builder!
I know I'm pretty new to this game but I cant see I've done anything wrong and I have not had an unsatisfied customer before.. Have I done anything wrong here?
The customer is unhappy as the builder has said he cannot use the cable I had in position for the downlights? He has gone ahead and put the ceiling up and just left all the cable that I had neatly dangling up in the void which is now not reachable without lifting floorboards.
He had said that he would position all the downlight holes and just pull the cable through, but the customer has said that he said the cable was not in the right position and would leave a big gap in the middle of the kitchen.
I specifically left plenty of cable (about 1.5m) dangling from the ceiling at each point so he could choose where he positioned the downlights and I spaced them out fairly evenly (as much as you can when just hanging from joists waiting for the ceiling to go up). So apart from the fact that it doesn't make sense, it would have been a good idea to call me before putting the ceiling up and hiding all my cable?
I cant get hold of the builder!
I know I'm pretty new to this game but I cant see I've done anything wrong and I have not had an unsatisfied customer before.. Have I done anything wrong here?