Re: My MCS reg installer does not think my 4KW system needs registering with the DNO
Western Power Distribution definitly allow up to 3.9kWp systems under G83 and also send a confirmation letter to us everytime, we then pass a copy onto the client. To test if this was correct i once sent them a G59 application up front, only to be told to send G83 doc when the project was completed, I like WPD!
My bet is that it depends on who you talk to or who process's the paperwork, not right but that seems to be the way of the world lately
Western Power Distribution definitly allow up to 3.9kWp systems under G83 and also send a confirmation letter to us everytime, we then pass a copy onto the client. To test if this was correct i once sent them a G59 application up front, only to be told to send G83 doc when the project was completed, I like WPD!