Good evening people.
I'm about to price up a kitchen we wire for a friend
I've done work for mates before and know how it goes.
Anyway, was hoping to get some guidance as I'm an improved and steadily taking on larger jobs myself.
Job:
Kitchen rewire.
3 sockets 3 single sockets chased in
4 spurs plastic under cupboards
Extractor Fan supply
6mm supply to new hob
New boiler supply
Upgrade bonding
Upgrade Consumer unit to split load 8 way. Same location
The run is an easy run as the consumer unit is currently mounted by the coving 3 meters from kitchen with an open clear loft.
I can't sign this off myself however I know someone who will test it after me and notify building control and issue cert (completed my apprenticeship with them)
I'll also test everything myself before asking them to come in and do this.
Customer supplies the face plates on show
I'll supply cable consumer unit fixings plastic spurs capping
I was thinking around ÂŁ200 for materials followed by ÂŁ400 labour and around ÂŁ70-ÂŁ100 for my mate to test and cert?
Time scales I'm allowing around 3 days 5 hours for consumer unit as it's old as ---- need to extend cables or 're run new ones to first points
That leaves enough for first and second fix of kitchen.
Open to suggestions and thanks for reading
I'm about to price up a kitchen we wire for a friend
I've done work for mates before and know how it goes.
Anyway, was hoping to get some guidance as I'm an improved and steadily taking on larger jobs myself.
Job:
Kitchen rewire.
3 sockets 3 single sockets chased in
4 spurs plastic under cupboards
Extractor Fan supply
6mm supply to new hob
New boiler supply
Upgrade bonding
Upgrade Consumer unit to split load 8 way. Same location
The run is an easy run as the consumer unit is currently mounted by the coving 3 meters from kitchen with an open clear loft.
I can't sign this off myself however I know someone who will test it after me and notify building control and issue cert (completed my apprenticeship with them)
I'll also test everything myself before asking them to come in and do this.
Customer supplies the face plates on show
I'll supply cable consumer unit fixings plastic spurs capping
I was thinking around ÂŁ200 for materials followed by ÂŁ400 labour and around ÂŁ70-ÂŁ100 for my mate to test and cert?
Time scales I'm allowing around 3 days 5 hours for consumer unit as it's old as ---- need to extend cables or 're run new ones to first points
That leaves enough for first and second fix of kitchen.
Open to suggestions and thanks for reading