S
steviec_lj
Hi folks,
Please do excuse me if this is in the wrong area, it covers a couple of topics so I thought it would be best to pop it in here.
A little over 2 weeks ago, we had a brand spanking new heating system installed, and I cannot fault the lads that came and did it. Everything was tidied up, they moved whatever they needed to, etc, etc. Unfortunately the same couldn't be said for the electricians that eventually came out and connected the
boiler, motorised valves and room stats up. If there were a rogues gallery, I could post a number of pictures up.
The main issues that I currently for see, is the bonding arrangement that they have installed. The main bonding for the water main seems satisfactory, and is connected after the stopcock, within 600mm of where the main enters the building. The have piggybacked from this, through the wall to the oil pipe, to a point on the oil pipe that is some 4mtrs away from where it enters the building and 2mtrs from an external stop tap. They have added bonding to all other pipe work near the boiler (Zone 1 feed, Zone 2 feed, Return, DHW and Mains Cold), externally they've added bonding to the pipe work either side of the metal de-aerater but not the filter, and from what I can tell, this renders the bonding useless?
The other issue that was brought to my attention this morning, when the envelope hit the mat, was that they appear to have done some testing of the circuit that they installed, and the bonding. Without actually testing it to the best of my knowledge. I wonder if anyone would be able to enlighten me as to how this would be possible, or alternatively, possibly linking to an image of the equipment used to test Earth Fault Loop Impedance, RCD operating times and Insulation Resistance.
I won't include any images at the moment, as I should really take their names off of a couple of them before I post them up. But I do believe I will be contacting NICEIC about the work that they have done, and also notifying the Plumbing company of their work.
Any advice, or tips on dealing with something like this would be great.
Steve
Please do excuse me if this is in the wrong area, it covers a couple of topics so I thought it would be best to pop it in here.
A little over 2 weeks ago, we had a brand spanking new heating system installed, and I cannot fault the lads that came and did it. Everything was tidied up, they moved whatever they needed to, etc, etc. Unfortunately the same couldn't be said for the electricians that eventually came out and connected the
boiler, motorised valves and room stats up. If there were a rogues gallery, I could post a number of pictures up.
The main issues that I currently for see, is the bonding arrangement that they have installed. The main bonding for the water main seems satisfactory, and is connected after the stopcock, within 600mm of where the main enters the building. The have piggybacked from this, through the wall to the oil pipe, to a point on the oil pipe that is some 4mtrs away from where it enters the building and 2mtrs from an external stop tap. They have added bonding to all other pipe work near the boiler (Zone 1 feed, Zone 2 feed, Return, DHW and Mains Cold), externally they've added bonding to the pipe work either side of the metal de-aerater but not the filter, and from what I can tell, this renders the bonding useless?
The other issue that was brought to my attention this morning, when the envelope hit the mat, was that they appear to have done some testing of the circuit that they installed, and the bonding. Without actually testing it to the best of my knowledge. I wonder if anyone would be able to enlighten me as to how this would be possible, or alternatively, possibly linking to an image of the equipment used to test Earth Fault Loop Impedance, RCD operating times and Insulation Resistance.
I won't include any images at the moment, as I should really take their names off of a couple of them before I post them up. But I do believe I will be contacting NICEIC about the work that they have done, and also notifying the Plumbing company of their work.
Any advice, or tips on dealing with something like this would be great.
Steve