Whats everyone's thoughts on this?
I've been asked to finish off another sparks work. I've not looked at the job yet, but know it mainly involves central heating wiring.
The customer says that the electrician that has done the work up to now cant find the time to finish off, and the heating engineer would like to commission his work.
There has been a number of delays for the customer already and he doesn't want another one.
I don't know if the original spark has been told he's no longer required.
I'll test the supply to the heating, but not the whole installation (unless they ask me to)
If I find something wrong with the rest of the house, do I drop the original spark in it? (I'll post pics here if there is )
I've been asked to finish off another sparks work. I've not looked at the job yet, but know it mainly involves central heating wiring.
The customer says that the electrician that has done the work up to now cant find the time to finish off, and the heating engineer would like to commission his work.
There has been a number of delays for the customer already and he doesn't want another one.
I don't know if the original spark has been told he's no longer required.
I'll test the supply to the heating, but not the whole installation (unless they ask me to)
If I find something wrong with the rest of the house, do I drop the original spark in it? (I'll post pics here if there is )