Do you need to install an RCD on a TT installation before a metal consumer unit if all the outgoing sub-main and final circuits are RCD/RCBO protected? The answer is no
RCDs, metal consumer units and TT installations | NAPIT
NAPIT's Bill Allan answers another common contractor query. Contractors sometimes ask whether it's necessary to install an RCD in a TT installation before a metal consumer unit (i.e. a 'front end' RCD
professional-electrician.com
you can avoid 10 minutes reading it if you want and skip to the last line, which is what NAPIT could have done.
Do you need to install an RCD on a TT installation before a metal consumer unit if all the outgoing sub-main and final circuits are RCD/RCBO protected? The answer is no