Got called out to a hairdressers yesterday after they were receiving shocks from a hair straiteners
Got there to find a single phase consumer unit no RCDs in site and no main earth or bonding at all
So remedy that by putting a temp earth rod in and bonding to water and gas
I have said that it requires a distribution board upgrade and RCDs installed on the shower and socket circuits. As the exsisting consumer unit is a mess
There is a 3phase supply and a 3 phase meter so the customer is being charged for the supply.
They have just lifted the brown phase out of the 3phase isolator and fitted a single phase consumer unit.
Should I keep the supply and quote to install a 3phase distribution board and split the circuits over the 3 phases
Or seeing as the customer isn't using the supply tell them and go down the root of getting the meter changed and upgrading the single phase consumer unit
What would you do ??
Got there to find a single phase consumer unit no RCDs in site and no main earth or bonding at all
So remedy that by putting a temp earth rod in and bonding to water and gas
I have said that it requires a distribution board upgrade and RCDs installed on the shower and socket circuits. As the exsisting consumer unit is a mess
There is a 3phase supply and a 3 phase meter so the customer is being charged for the supply.
They have just lifted the brown phase out of the 3phase isolator and fitted a single phase consumer unit.
Should I keep the supply and quote to install a 3phase distribution board and split the circuits over the 3 phases
Or seeing as the customer isn't using the supply tell them and go down the root of getting the meter changed and upgrading the single phase consumer unit
What would you do ??