EDF have requested a building be converted to a TT system.
Currently a TNS 2x100a head supplies a shop then a flat respectively.
The are x2 fuse boards supplying the two areas each having 30ma RCD protection on all final circuits.
Am I correct in saying in simple terms X1 earth spike Into ground, separate the TNS - TT earthing systems from each other and x2 200ma time delay main RCD switches on the two supplies on the meter tails for each supply.
Currently a TNS 2x100a head supplies a shop then a flat respectively.
The are x2 fuse boards supplying the two areas each having 30ma RCD protection on all final circuits.
Am I correct in saying in simple terms X1 earth spike Into ground, separate the TNS - TT earthing systems from each other and x2 200ma time delay main RCD switches on the two supplies on the meter tails for each supply.