hi
I've been pulling my hair out trying to finish a installation on a farm , but now i'm very stuck on what i can do
sec are upgrading the three phase supply to 200A and putting in a CT chamber, previously there was several supplies going to CUs from henley blocks and tails but now its being uprated and sec have asked me to put in 70mm tails i can no longer put them into henley blocks.
so what ives done is put a Iline board in and had all the existing CUs as sub boards feed via the Iline.
But now sec have come back and said because its a TT system and a farm that it needs a 300ma RCD, which is fair enough but Iline panels dont have RCD protection and neither can i find any RCD protection for anything above 125A RCCB main switch, nothing that will fit 70mm tails or 200A,
Please can someone help as Im really stuck
I've been pulling my hair out trying to finish a installation on a farm , but now i'm very stuck on what i can do
sec are upgrading the three phase supply to 200A and putting in a CT chamber, previously there was several supplies going to CUs from henley blocks and tails but now its being uprated and sec have asked me to put in 70mm tails i can no longer put them into henley blocks.
so what ives done is put a Iline board in and had all the existing CUs as sub boards feed via the Iline.
But now sec have come back and said because its a TT system and a farm that it needs a 300ma RCD, which is fair enough but Iline panels dont have RCD protection and neither can i find any RCD protection for anything above 125A RCCB main switch, nothing that will fit 70mm tails or 200A,
Please can someone help as Im really stuck