Metal enclosure, plastic front cover, mismatched RCDs that push them out of line.. could get a new board for £70 ish, but no, got this load of carp instead!!

IMG_20200123_120119.jpg
 
Dealing with the results from an EICR carried out by niceic ac contractractor at a commercial premise at the moment. 6 out of 7. Ccu"s have been condemned as C2's, no other reason given than combustable, checked for damage, ip, thermal, nothing. 7th escaped extinction due to having a non combustable enclosure, which has a plastic cover. Rang niceic tech line, other than things checked for not warranted. On a walk around with no testing or getting a ladder out or plate of ---- loads of C2's not on the report.

No logic sometimes.
 
Dealing with the results from an EICR carried out by niceic ac contractractor at a commercial premise at the moment. 6 out of 7. Ccu"s have been condemned as C2's, no other reason given than combustable, checked for damage, ip, thermal, nothing. 7th escaped extinction due to having a non combustable enclosure, which has a plastic cover. Rang niceic tech line, other than things checked for not warranted. On a walk around with no testing or getting a ladder out or plate of ---- loads of C2's not on the report.

No logic sometimes.

The board in the piccy above is semi combustible I guess !! Never seen a mishmash of sh1te gathered together like that though..
Insulated enclosures are very rarely a C2 in my book.
 
Dealing with the results from an EICR carried out by niceic ac contractractor at a commercial premise at the moment. 6 out of 7. Ccu"s have been condemned as C2's, no other reason given than combustable, checked for damage, ip, thermal, nothing. 7th escaped extinction due to having a non combustable enclosure, which has a plastic cover. Rang niceic tech line, other than things checked for not warranted. On a walk around with no testing or getting a ladder out or plate of ---- loads of C2's not on the report.

No logic sometimes.

There's no requirement for non combustible CUs in a non domestic installation at all.
 
Dealing with the results from an EICR carried out by niceic ac contractractor at a commercial premise at the moment. 6 out of 7. Ccu"s have been condemned as C2's, no other reason given than combustable, checked for damage, ip, thermal, nothing. 7th escaped extinction due to having a non combustable enclosure, which has a plastic cover. Rang niceic tech line, other than things checked for not warranted. On a walk around with no testing or getting a ladder out or plate of ---- loads of C2's not on the report.

No logic sometimes.
sounds like somebody fishing for remedials that are not required. they need reporting to niceic. fat chance of anything being done though as long as their subs are paid.
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread starter

NDG Elecs

Arms
-
Joined
Location
Tyne and Wear
If you're a qualified, trainee, or retired electrician - Which country is it that your work will be / is / was aimed at?
United Kingdom
What type of forum member are you?
Practising Electrician (Qualified - Domestic or Commercial etc)

Thread Information

Title
Why, just why !!
Prefix
N/A
Forum
UK Electrical Forum
Start date
Last reply date
Replies
9
Unsolved
--

Thread Tags

Advert

Thread statistics

Created
NDG Elecs,
Last reply from
telectrix,
Replies
9
Views
1,315

Advert

Back
Top