Hey guys, I have a major problem. I have just run in 40 submains and re powered the communal's in a pre-existing block of flats. The company I'm doing the work for will not pay me until the communal TV system is up and running. That's got nothing to with me. Sadly, they thinks it does. They are claiming that I agreed to fit and install the TV at the same time as the duct work for each flat. They asked me to quote for it. I didn't. They presumed it was in the quote, though written in invisible ink, cause it certainly wasn't.

They owe me thousands. And, I do mean the wrong side of 7k

I have to fit an MATV system. The one block of 40 units is divided into 2 blocks of 20 units, in Southampton. There is two Lucy boards with two landlords supplies available.

Recommended type of Aerial? Boosters?

This is my plan - install two MATV systems for each 20 units. I know that I need to bring the signals to all the units (using satellite cable for this - not shotgun, only digital TV required). My plan is to install two high quality Digital TV Aerials on the roof. Run two cables from it to two 12 way Boosters. This would apply for both sides of the 20 units. All of the cables going to the units as well a from the aerial will be earthed due to the potential earth leakage from each unit. I also need to buy a reasonably priced TV signal meter.

I have to be honest here guys. This is my Christmas money for the family at stake here. My wife does not know. This company is becoming very difficult. I will be paid the final instalment. There's been no money problems before

Any advice is gladly received, I can't afford to have two Christmases in a row with my kids masking their dejection

Please, No screaming preachers about legal action, or get a professional in, I have tried, once they hear the above they are walking away, and won't even advise me


It should be noted that the client has agreed that I locate the new TV outlet in each unit adjacent to the new power supply, this is for the new owners to take it from there.
 
I dont get where you are coming from,if there was no written specification with TV included,and it is not in the quote from you that they accepted...then why are you doing it?
Cant help thinking you are not telling the entire story here.
 
I can see the outcome of this being you installed the submains and then the T.V and get paid NOTHING.

Be very wary of whoever you are dealing with, they can't make you install something you haven't even quoted for.
 
Hey guys, I have a major problem. I have just run in 40 submains and re powered the communal's in a pre-existing block of flats. The company I'm doing the work for will not pay me until the communal TV system is up and running. That's got nothing to with me. Sadly, they thinks it does. They are claiming that I agreed to fit and install the TV at the same time as the duct work for each flat. They asked me to quote for it. I didn't. They presumed it was in the quote, though written in invisible ink, cause it certainly wasn't.

They owe me thousands. And, I do mean the wrong side of 7k

I have to fit an MATV system. The one block of 40 units is divided into 2 blocks of 20 units, in Southampton. There is two Lucy boards with two landlords supplies available.

Recommended type of Aerial? Boosters?

This is my plan - install two MATV systems for each 20 units. I know that I need to bring the signals to all the units (using satellite cable for this - not shotgun, only digital TV required). My plan is to install two high quality Digital TV Aerials on the roof. Run two cables from it to two 12 way Boosters. This would apply for both sides of the 20 units. All of the cables going to the units as well a from the aerial will be earthed due to the potential earth leakage from each unit. I also need to buy a reasonably priced TV signal meter.

I have to be honest here guys. This is my Christmas money for the family at stake here. My wife does not know. This company is becoming very difficult. I will be paid the final instalment. There's been no money problems before

Any advice is gladly received, I can't afford to have two Christmases in a row with my kids masking their dejection

Please, No screaming preachers about legal action, or get a professional in, I have tried, once they hear the above they are walking away, and won't even advise me


It should be noted that the client has agreed that I locate the new TV outlet in each unit adjacent to the new power supply, this is for the new owners to take it from there.

Obviously you are not being entirely truthful,if there was no contract to do the work then you will be well aware that you cannot lose legal proceedings so you would have got legal representative at no expense spared,as the company you are suing would be made to pay the bill.
Why are you even considering being ripped off like this? The small claims court would have this sorted out within 28 days..so that would be in time to avoid a 2nd Christmas eating toast while watching the queens speech :)
 
Obviously you are not being entirely truthful,if there was no contract to do the work then you will be well aware that you cannot lose legal proceedings so you would have got legal representative at no expense spared,as the company you are suing would be made to pay the bill.
Why are you even considering being ripped off like this? The small claims court would have this sorted out within 28 days..so that would be in time to avoid a 2nd Christmas eating toast while watching the queens speech :)

Payment within 28 days of the result of the claim. Might take 6 months to get a date for the hearing, maybe longer, and laying out a good few quid when you book it. Seen it......done it, and well worth going down the route.....he'll eat a good christmas dinner in 2015
 
The way I see this is it all comes down to the wording both parties have used. If they have asked you to quote for all items on (let's call it) list A and you have not itemised exactly what you're quoted for then you're up poo creek without a paddle.
In your situation I'd talk to whoever is responsible at the other end (calmly of course) and explain the situation as you see it, you can then tell this person that the additional work (keep calling it this) is £x and you want written confirmation of their acceptance of the quote.
If they agree then everything is hunky dory again and you can then ask them for a payment on account of this £7k+
I wouldn't bother with talking to any of the monkeys though mate, go straight to the organ grinder.
 
I would Go with Trevor's advice on this one.
Also in this day and age of everybody wanting every thing for nothing and everybody trying to wriggle out of their responsibilities it is paramount that you produce a precise and accurate quotation for all work to be carried out and that anything not on the quote will be additional and this must be agreed by all parties involved.
An additional thought and not meant to kick you while you're down but maybe ask for some advice when submitting future quotes, because to be going through this for a 2nd Christmas running means either yo are extremely unlucky or you are doing something wrong.
 
I don't know jack about TV systems but surely someone could advise the man? Seems like a **** situation to be in.
 
Well obviously the guy has never heard of stage payments or valuations as we more experienced business men call them. I would never install 40 sub-mains without some payment during and the rest straight after, well 30 days max, thats just plain crazy doing a job complete then waiting to get paid.
 
Well obviously the guy has never heard of stage payments or valuations as we more experienced business men call them. I would never install 40 sub-mains without some payment during and the rest straight after, well 30 days max, thats just plain crazy doing a job complete then waiting to get paid.
or interim payments as even more experienced business men call them.
 
Best EV Chargers by Electrical2Go! The official electric vehicle charger supplier.

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
Please Help Christmas mony at stake MATV System for a block of 40 flats
Prefix
N/A
Forum
Electrical Wiring, Theories and Regulations
Start date
Last reply date
Replies
33

Advert

Thread statistics

Created
biscuits,
Last reply from
High Tower,
Replies
33
Views
3,310

Advert

Back
Top