Hello Richard
I see, hope you have deep pockets. another solution might have been to add battery storage on what you already have & not bother with the additional panels. not sure if 1.645kw of additional panels would give you a return on investment with G59/3 relay & install, I know you are not...
could you let us know if the insulated ducting is part of the fan make up or if that is doing something else. wherever possible I try & use rigid ducting even if it means covering in insulation in cold space (loft), flexible ducting is ok on small runs but you mostly always get that type of...
Hello Richard
so you would like to add battery storage system to your 3.68Kw system am I correct?
not sure why you need a G59/3 hook up & certificate.
unless I have missed something.
would they be the old style tails they used to use with what looked like a woven sheath on the outside, still come across them today, has he come back with answer yet or picture ?
Dlt27
I agree with all the above safety first, but you could drop motor out of Overload & then do some tests, check E/Stops then work through diagram looks simple enough with coil information & following the route of your auto SW.
at least you have a drawing to follow might not be the best or...
been out to two EICR reports last few months both for people buying a house, well first 12 circuits 3 tested rest dashes throughout of the 3 the oven was one & the switch had not been removed as when I did the tiling dust & build dust all fell out & you could not move the range unit on your own...
Hi n180
state in your terms & conditions a warranty period for all items supplied & fitted (we offer 12 months), this does not affect manufacturers warranty but does allow after the 12 months for you to charge labour for the replacement of the unit.
also worth stating in terms & conditions your...
check with DNO first if they have capacity on the local transformer to cover the full load, should they be close to capacity they might even allow install but you might have to install a new transformer or even be directed to connect to another transformer further away, they may even limit...
Hi Marvo
just had to report my findings to the engineer to determine if he wanted to visit site or not to have a look at works, all done by photos & readings he was happy with readings & photos of works.
I was contacted yesterday to ask to supply certificate for the works & requested to be at...
Hi All
late last year & early part of this year we had been asked to install customer HV earth system & LV earth system to a drawing supplied.
all went well after some messing around trying to get Rods installed in frozen & water logged trench.
all readings fine & the cad weld system all went...
looked okay no signs of water damage any location, the testing & running of the heater was also taken remove from any other part of the circuit so just the heater in use.
Oh well now I have the nice job of changing the heater, just glad I bough that earth leakage unit a few years back as I ruled out heater due to the IR & continuity being good just goes to show.