Hi guys I'm searching for information relating to the AM2 I've got it booked for the 12 of November I'm also in the process of completing the NVQ3 which is taking ages as I am working on trains at the moment and theres not much installing just doing continuity and IR testing so completing my...
Hi everyone,
Done my am2 composite instal today and whilst sitting at home just realised i have not put my compression rings on my SWA.
two questions, is that a straight fail? can i adjust during my test inspect?
just had to drive like a nut nut to screwfix to get a gland...
Hi,
This is my first post, although I have been browsing the forums for a little while now.
I work in BMS and have my AM2 on friday. The nature of my work means I don't get to test so there are a few things I'm unsure of and was hoping for some clarification.
I know for some people they may be...
So got my am2 tomorrow up in birmingham. Heading up tonight so im not traveling nearly 2 hours there and back each day.
Anyome got any advice or tips for it as im very nervous.
Also what is that green and yellow wire...is this important??
Hi guys
Ive been booked in for my am2 for the 2nd week of october.
My employer and college have been really big helps in sorting me out for the practical side of it by going over everything with a fine tooth comb so its really drummed in.
But im also concerned regarding the online exam. I...
Hello people, just finished my Am2 today and all went well, finished everything and didnt really have an issue with anything in regards to install, testing and fault finding. But... when we finished i asked the examiner what are some of the mistakes people make. And he said installing the wrong...
I have almost finished my NVQ Portfolio and will soon be booking my place at an am2 test centre. I know there is a long waiting list at some of these places and I wonder if the exams will be changed at all by the time I take mine?
To be more specific, does anyone know whether there will be an...
Hello all, new to the forum and everyone seems to be quite frendly and happy to help out. So.. i have my am2 in a few weeks and am pretty gemmed up on everything but there are a few things bothering me. And have checked all forums regarding am2 prep and can't seem to find anything.
1.When...
Hi. I've got a resit for the Am2 in a month as I failed the socket circuit. The problem is, I'm not sure how ! I've drawn a quick diagram of the wiring they give you and how I would wire it.
The top drawing is the diagram they give you..
hi everyone ,
I’ve just completed my am2 I think I did fairly well on everything the only thing that’s bugging me is, on my shedual of test results I’m sure I put the wrong size cpc for the c/o detector circuit.
I put the cpc as 1mm however I think it was 1.5 would this one thing cause me to...
Hi all,
Sadly I have to retake the fault finding section of the AM2 next Monday.
We used a multimeter to determine faults.
There are millions of types of fault, however only 4 types of wiring faults are being tested:
Open Circuit = unambiguous/obvious = no ohm reading.
High Resistance =...
Hi all,
Been posting on here quite a bit the last couple of weeks, been really helpful and good advice.
I am sitting my am2 next week. Just wondering if any one has any advice? What to expect from fault finding etc. Thanks
i have my am2 coming up soon. Was just curious as to how you test the dol tobthe motor after doing the global IR test, testing strappers and ring etc. Do you test from the dol going to the motor, or from the motor to the DOL, or does it matter?
Any advice would be great. I have used this forum...
hi all,
I have my am2 coming up. Just going over a few things. I am correct in saying that the Gas bonding would terminate in to the clamp below the joint, and not above it?
Also, I was going to use one continuous length of 10mm is this allowed, or is it better practice to use to lengths?
Regards
hi all Ive just started my level 2 & 3 fast track course full course is 10 months for both qualifications doing it on sat and sun as i work Moday to Friday as a HGV driver and transport manager once I've completed the course it will be time to get the experience working i have family who are in...
Hi,
Can anyone who has passed there AM2 please tell me what size fuse they used for the sy heating plan. It is fed from a B16. So, would it just be a 13a? I have seen them just on a 3a before.
Cheers
Hi,
Could someone who has completed their AM2 please give some advice?
When commencing your ze, pefc, PSCC.
Do you set your megger tester to high or low.
I would normally set it to high for the ze, pefc and PSCC tests?
Although, I have been it should be set in low because of the RCBO on the...
hi everyone,
When demonstrating safe isolation on the lighting circuit on am2 do you operate the switches and test each time you operate.
Or, just operate the switches in every position then just test once at the 2d light fitting?
Also, when commencing a ZE test would you recommend setting the...
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc