Hello
I am taking my AM2 in 8 weeks and have some questions that I was hoping you guys could answer for me?
1. Does the pre-installed metal containment require earthing?
2. When wiring the RFC do you follow the specification (with a long leg from the final socket-outlet back to the board or can you wire it so that that you keep the cable runs relatively equal?
3. Do you need to sleeve/identify the numbered cores on the SY cable for the motor circuit?
4. If the external socket-outlet is to be fed from the FCU, do you connect it to the load side (protected by the 13A fuse)?
5. What exactly is a bridging section when installing Cat5 cable in multi-compartment PVC trunking as I have not seen one before?
6. Is it okay to ask the assessor for the DNO Ze value or are you expected to measure it?
7. Is the luminaire usually a 2D 28w?
Thanks
I am taking my AM2 in 8 weeks and have some questions that I was hoping you guys could answer for me?
1. Does the pre-installed metal containment require earthing?
2. When wiring the RFC do you follow the specification (with a long leg from the final socket-outlet back to the board or can you wire it so that that you keep the cable runs relatively equal?
3. Do you need to sleeve/identify the numbered cores on the SY cable for the motor circuit?
4. If the external socket-outlet is to be fed from the FCU, do you connect it to the load side (protected by the 13A fuse)?
5. What exactly is a bridging section when installing Cat5 cable in multi-compartment PVC trunking as I have not seen one before?
6. Is it okay to ask the assessor for the DNO Ze value or are you expected to measure it?
7. Is the luminaire usually a 2D 28w?
Thanks