within a building supplied my a PME system it’s not possible to main bond the extraneous conductive parts effectively back to the origin.
Resolution instead of changing to a TT system remove the extraneous conductive parts.
Water pipe: this comes out the ground so change this to plastic and put a stop cock on the plastic section then box it off.
Soil stack: simply just box it in.
Can anyone see anything wrong with that? Saves allot of agg
Resolution instead of changing to a TT system remove the extraneous conductive parts.
Water pipe: this comes out the ground so change this to plastic and put a stop cock on the plastic section then box it off.
Soil stack: simply just box it in.
Can anyone see anything wrong with that? Saves allot of agg