dannym
Hi everyone, I've rewired my first house by myself - I havnt done a great deal of domestic work, mainly industrial and commercial. But I've got a few of questions that I havnt been able to find answers for. I think I know how to do them but would just like some conformation to boost my confidence with it lol.
1. On one lighting circuit I've taken the feed to 3 different rooms, and they are feeding 2 pendant lights and one extract fan and in the kitchen - 10 led downlights. My question is will these 10 downlights be ok on one switch? Or will it overload the circuit?
2. The external shed requires a feed. The shed is approximately 25m away from the consumer unit. My idea is to run a 2 core 6mm SWA to an IP rated adaptable box on the side of the house and connect a 6mm t and e into this and run it back to the board. Would this be acceptable? I know that I need an earth stake near the shed.
3. The board is moving the meter to an external location (the consumer unit has also been moved). But is over 3m away from the meter. I was going to use a KMF switch that would be boxed in somehow and use an SWA out of if to an IP rated adaptable box and then feed the consumer unit. Does this sound ok or does anyone have any other suggestions? I've never dealt with the electricity company directly before and the customer has spoke to them so I'm not sure what they'll leave me with.
Many thanks,
Danny
1. On one lighting circuit I've taken the feed to 3 different rooms, and they are feeding 2 pendant lights and one extract fan and in the kitchen - 10 led downlights. My question is will these 10 downlights be ok on one switch? Or will it overload the circuit?
2. The external shed requires a feed. The shed is approximately 25m away from the consumer unit. My idea is to run a 2 core 6mm SWA to an IP rated adaptable box on the side of the house and connect a 6mm t and e into this and run it back to the board. Would this be acceptable? I know that I need an earth stake near the shed.
3. The board is moving the meter to an external location (the consumer unit has also been moved). But is over 3m away from the meter. I was going to use a KMF switch that would be boxed in somehow and use an SWA out of if to an IP rated adaptable box and then feed the consumer unit. Does this sound ok or does anyone have any other suggestions? I've never dealt with the electricity company directly before and the customer has spoke to them so I'm not sure what they'll leave me with.
Many thanks,
Danny