Hi All,

I am due to wire a small industrial unit, they want 14 double sockets 10x 3phase 16 amp sockets, a new mains board and all wired in swa cable on metal tray.
The gear will cost around £1000.00. was thinking around a week to install.
can anyone give me a ball park figure for the whole job?
Ive to test and certify all work also. many thanks
 
just multiply by 5 like a big gun would, on a serious note only you should know whats involved but sure someone has few points to make as they have done it lots of times. and welcome
 
5 @ 8 hours a day @ 35 pound an hour x = 1400 for labour 1000 plus mark up of 15% = 1150 so ball park would be 2500 pound.

As it is commerical you should charge a little more than you normally do for domestic. In the good old days you could have charged over 50 pounds an hour in the SE but times have changed, and you would know your area and market.
 
i would have thought that it would pay you to have a mate with you for the containment and pulling cables. either add his wages for the week, or recalculate your timespan for 2 ( maybe do it in 4 days ) and price accordingly. e.g. your labour for 4 days + £400 for the mate.
 
Thanks guys for your input.

Just checked the drawing...there is 12 machines all rated at around 5.5kva.

I was going to run a 2.5mm 4core to each machine and put each machine on a 16a tp breaker at the board.

Im a pretty new small business and havnt done a lot of new 3 phase installs as work mainly on domestic and commercial.

Is there a better way of doing the above or am I right doing this? it just seems like a lot of breakers and a big board for a small unit.

i.e. could I put two machines on the one breaker?

Ps only joined electricians forum yesterday,Was always a little sceptical.
How wrong I was as you guys have been so helpful. many thanks
 
best practice would be each machine on its own dedicated radial and MCB. least of all , if there was a fault on a circuit, only 1 machine would be lost, and each machine can be individually isolated. IMO the only way to go.
 
How big is the area, and how long would the runs be. You could think about doing the install as a couple of Ring Circuits.
 
What type of business is it, and will those 12 machines be operated continuously during working hours. When working in Industrial type units/factories, careful assessment of installation requirements need to be ascertained, before the final design of such installations...
 
It is going to be a joinery shop and the machines are saws, routers etc.
The building is about 25 metres by 12.

Didnt think you could run 3 phase in a ring?

The furthest cable run would be around 30 metres.

Was going to suspend some tray across at high level hung on catenary wire.
 
If you give me all the runs materials etc I'll run it through our estimating system, need each run tray runs cable ets as per previous post
 
NO, PLEASE, DO NOT RUN A 3ph RING.
YOU WILL NOT comply with legislation.
Listen to Engineer54.
You need to run individual supplies to each machine to comply with both 7671 & other statutory regs.
There are also considerations in 7671 you may not think about, check the brb carefully to ensure compliance in wood working premises.
It is easy to install a non compliant installation without realising!
 
cable tray 6" =35 mtrs

3ph runs: 4x 30mtr, 3x 25 mtr,2x 20mtr, 3x 10 mtrs

14x 230 d/skts dotted around perimeter of building 25mtrx 12 ish pprob run in swa or pvc conduit and singles

Is there a website that you can get a reliable estimating program that is easy enough to use?
 
Its a joinery shop only manned by 1-2 people.

therefore probably only 2 machines used at any one time.

thanks for your help
 
£6,018.77 inc all fixings etc labour rate @ £24.65 inc our discounts plus 15% however this is based on the information you have given and does not include working at over 2m
 
Best EV Chargers by Electrical2Go! The official electric vehicle charger supplier.

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
Small industrial unit, advice on pricing
Prefix
N/A
Forum
Electrician Talk | All Countries
Start date
Last reply date
Replies
58

Advert

Thread statistics

Created
mgnelec09,
Last reply from
davelerave,
Replies
58
Views
8,337

Advert

Back
Top