Alot of the properties I work in, were built when the 16th Edit ruled, most with no RCD's for bathroom lighting. Majority have evidence of supplementary bonding, clamps & earth wires on basin pipework, rads etc, or in immersion heater cupboards. However, some have no sign of that. Now I've read reg 701.415.2 & 415.2.2, so you can test for the effectivness of the earthing, but I never worked under the 16th Edit, so what should I expect to see. I've mentioned earth clamps etc, but the wiring diagrams I've seen, show bonding from cpc's to extraneous conductive parts, how do you connect a 4mm cable in a light fitting? I've also read on this forum, that the supplementary bonding should not go back to the MET, but I've seen tell tell signs of 4mm earth cables in CU? So how was it installed?