i agree with your post but i am positive i am testing it correctly,as i said in my original post,4 out of the 5 came back open circuit,but 1 which was the top floor flat tested ok R1+R2.
thanks for your input fellas i will try R2 method on monday and report back
 
Even if hes testing with main earth and bonding connected, then removing them ain't going to make an R1 R2 figure appear.

Must be testing wrong, if submains are T and E then can't see how R2 can be lost

But if he,s getting a Zdb reading he could be getting yhis through parrell paths of the bonding. When in actual fact he's got no earth. :thumbdown:

Sent from my GT-I9100 using Tapatalk
 
Hi All i know its late friday, but try and help me out with this one if you can.
Just got in now from work on the way home a landlord called me to ask if i could test a communal DB he has at an HMO.
I decided to have a look on the way home, long story short each flat was feed from this DB including the communal circuits(lights,sockets).
so i checked Zdb to each flat which was ok but when i did R1+R2 test on the supply cable to each flat i got nothing,tried to each flat and 4 out of the 5 came back with a zero reading.
Distribution board was contactum,each flat was feed from a 40 amp b type mcb (No RCD on DB).

Any thoughts as its got me wondering, the Zdb to each flat was ok but R1+R2 no reading at all.

Alright Delboy :D

Interesting thread btw.

Having re-read your opening post, I can only surmise that R2 for the sub main is broken for 4 of the 5 flats. As others have pointed out you may very well still get a cracking Zdb via parallel paths (spesh if Bonding in place for water service in each flat for example and this runs via pipework back to DB1 - the origin board so-to-speak).

So Mr R2 test will reveal all. Hopefully.
 
Are you sure the circuits are labeled correctly???

i.e you linked r1+r2 at DB circuit labeled flat1, testing at flat 1 but the r1+r2 circuit is actually flat 4?
 

Reply to Zdb ok but no R1 + R2 in the Periodic Inspection Reporting & Certification area at ElectriciansForums.net

News and Offers from Sponsors

  • Article
Join us at electronica 2024 in Munich! Since 1964, electronica has been the premier event for technology enthusiasts and industry professionals...
    • Like
Replies
0
Views
311
  • Sticky
  • Article
Good to know thanks, one can never have enough places to source parts from!
Replies
4
Views
834
  • Article
OFFICIAL SPONSORS These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then...
Replies
0
Views
935

Similar threads

  • Question
if the 3 spaces with charge points are always allocated to the same 3 flats, surely the easiest way is to run the supply to the load side of the...
Replies
9
Views
901
I own a top floor tenement flat that I used to live in and then rented out after I married. It is currently empty whilst some work is being done...
Replies
0
Views
579

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top