N

Noob2013

Hi all,

I have been to a property where the tails come out of the meter and into an RCCB which then feeds the main switch of the consumer unit. All circuits are protected by MCBs.

If I'm adding a new circuit, is it best put in an RCBO instead of an MCB?

Thanks
 
My point was if he installs a new circuit to a board which has a RCD main switch (and doesn't need it) then in affect he will be making the existing circuits worse by adding to the problem of one RCD protecting the whole installation. I know it is not clear cut and is only my interpretation so I think a board change would ensure all the new work is compliant.

i agree, but you border on persuading the customer to spend more than necessary if a less costly solution is available whilst still leaving the installation safe. a bit like condemning 3036 boards because they're not to current standards, although safe for continued use.
 
Where would you use one?
I know where you find them, next to the rocking horse sh*t lol

Main and sub distribution units used for temporary power distribution in outdoor events will often incorporate adjustable RCDs which can be set to give 30mA time delayed operation along with a whole host of other possible settings.

Most rental generators now have adjustable RCD protection as standard too.
 
Main and sub distribution units used for temporary power distribution in outdoor events will often incorporate adjustable RCDs which can be set to give 30mA time delayed operation along with a whole host of other possible settings.

Most rental generators now have adjustable RCD protection as standard too.

Hi Dave

But why would you want to set it at 30mA delayed as opposed to 100mA delayed , as by delaying it you will have lost the benefit of the 30mA anyway ?
Is this something to do with the regs you have to follow for events
 
Ok. I think we can safely say the OP's client will not have a bespoke "specialist order" variable ma RCD on the front end of his install. More like a crusty old 60A Crabtree ELCB that don't trip when the button is pressed!!
 
Hi Dave

But why would you want to set it at 30mA delayed as opposed to 100mA delayed , as by delaying it you will have lost the benefit of the 30mA anyway ?
Is this something to do with the regs you have to follow for events

To ensure discrimination with 10mA RCDs installed downstream of it. The same way you would use 100mA S type in front of 30mA in a TT setup. It depends entirely on what it is protecting and why.
You are building installations out of pre-built standard distribution boards unlike fixed installations so you almost always end up with multiple RCDs in series. Sometimes you have to set one as a 30mA time delay just to stop a fault on one circuit from tripping out 2 or 3 RCDs upstream of it but still give discrimination with a 100mA upstream of that.


There is no regulatory reason for using them though, just the individual electricians design/method for ensuring that faults cause minimum disruption.
 
Ok. I think we can safely say the OP's client will not have a bespoke "specialist order" variable ma RCD on the front end of his install. More like a crusty old 60A Crabtree ELCB that don't trip when the button is pressed!!

No he won't, but you stated that such things do not exist, so those of is who know better have disagreed.
 
I will have a look at the RCD when I go back and update you all.

It looked like a fairly new RCD with a test button. Definately not 10+ years old! Also no adjustments available on it.

So the general verdict is;

If it's a 30mA RCD then use an MCB for new circuit.

and

If it's 100mA RCD then use a 30mA RCBO for new circuit?
 
it is not quite that clear cut. You will need to interpret the regs on this one as there is a little disagreement.

I would say to be 100% sure just change the board. You cannot be wrong then. Other methods are open to a little interpretation.

Prepare 2 quotes and give the customer the pros and cons of both.
 

Reply to RCCB as main switch? in the UK Electrical Forum area at ElectriciansForums.net

Similar threads

Joining the ends of the radials together to form a ring, and changing the circuit protection to a single 32A would solve the MCB overload problem...
Replies
8
Views
669
Also use a tails gland and clamp if available and make sure tails are secured to a wall. The danger here is a live to earth fault in the Consumer Unit
Replies
7
Views
519

Recommended Sponsor News

Quickwire Now Sponsor ElectriciansForums.net

I am sure you will join me in welcoming our newest sponsors of ElectriciansForums.net - Quickwire! They have decided to join us after seeing you guys discussing their products here. Now we have an expert on board that you can chat to @Quickwire-Sam who will be happy to answer your queries!

[ElectriciansForums.net] Quickwire Now Sponsor ElectriciansForums.net


@Quickwire-Sam said "At Quickwire, we're all about speed, safety, and reliability. We're a family-run business, and every Quickwire connector is proudly made right here in the UK, ensuring noticeable quality. In short, Quickwire is the fastest connection method on the market. Whether you're an experienced electrician or a DIY enthusiast, Quickwire makes electrical connections ridiculously quick and easy. We're passionate about blending British craftsmanship with innovation. If you have any questions or if there's any way we can help, please just ask me!"

Exclusive Forum Offer! Free euro 2024 wall chart for first 10 responses!

Hi everyone,

We have 10 exclusive Uheat EURO 2024 Wallcharts to giveaway for Electricians Forum Members! The first 10 people to reply YES to this thread - I will message and get them sent out to you just in time for this years tournament! GO GO GO

PCBWay Now Sponsor ElectriciansForums.net!!

I hope you will all join me in welcoming our newest sponsor to the forum PCBWay! You can contact their friendly people by sending a message to @PCBWay who will be happy to answer your queries.

Welcome to the community and thanks for your sponsorship!

[ElectriciansForums.net] PCBWay Now Sponsor ElectriciansForums.net!!

PCBWay provides services including PCB Prototype and batch Production, PCB Assembly (SMT), 3D Printing, CNC Machining, PCB Design, Electronics Modules Selling, etc. We are committed to meeting the needs of global makers from different industries in terms of quality, delivery, cost-effectiveness, and any other demanding requests in electronics.

[ElectriciansForums.net] PCBWay Now Sponsor ElectriciansForums.net!!

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top