I need to terminate 16mm SWA 2 core cable in Wylex REC Supply Isolators. Going to be using armour for earth. Whats the best thing to do with the earth. I have 12 of these to install. The only idea I have is to terminate armour on steel trunking then run 2 cores into Wylex REC Supply Isolators. Lastly connect earth back to intake. I'm sure there is a better way, I dont want to use steel trunking unless I have to?